Dwar | Mysore Palace OperationsDelivery Tracker

Daily engineering progress for Livetree

22 Nov 2026 IST

Pre-trial build & daily delivery schedule

15-day engineering sequence leading to counter hardware verification on 5 December 2026 and full live cutover on 15 December 2026.

Build progress2/15 days
17%
Current sprint day
Day 03 / 15

22 Nov 2026 · Active today

Days to counter trial
13 days

5 Dec trial · 23 days to 15 Dec go-live

Delivery scope
6 modules

Ticketing, HR, Expenses, GST, P&L, Cloud

Today's Active Build · Day 03Ticketing & Gate POS
22 Nov 2026

Signed QR generation and single-entry gate scanner

Implement HMAC-signed QR ticket codes, gate scan verification, IST date validation, and duplicate entry protection.

  • Wiring HMAC-signed QR payload generation and cryptographic signature verification per receipt.
  • Adding IST visit-date mismatch detection with owner/manager override logging at entry gates.
  • Connecting webcam BarcodeDetector live QR scan fallback alongside manual gate code entry.

Module coverage (6 core pillars)

Updated live in IST

Ticketing & Gate POS

Active

Counter sales keyboard terminal, 80mm thermal tickets, signed QR gate validation, online booking, and day close.

1 of 4 days complete · 1 active38%

HR & Staff Operations

Scheduled

Employee KYC vault, Aadhaar/PAN/IFSC onboarding, daily attendance overtime, weekly roster, and payroll.

0 of 3 days complete0%

Expenses & Approvals

Scheduled

Petty cash and vendor expense capture, receipt file storage, approval workflow, and rejection tracking.

0 of 1 days complete0%

Accounting & GST

Scheduled

Double-entry chart of accounts, invoice OCR extraction, GSTR-2B matching, GSTR-3B export, and bank reconciliation.

0 of 3 days complete0%

Owner Dashboard & Exports

Scheduled

Live revenue and footfall KPIs, seasonality view, monthly P&L summary, and printable PDF/Excel/CSV registers.

0 of 1 days complete0%

Cloud & Counter Readiness

Active

Server hardening, role-based access controls, alert pipelines, encrypted nightly backups, and trial readiness.

1 of 3 days complete33%

Daily update timeline (20 Nov to 4 Dec)

Completed days list shipped capabilities; future dates stay marked scheduled with planned scope only.

Day 01
20 Nov 2026Cloud & Counter ReadinessCompleted

Cloud server setup, PostgreSQL schema, and access control

Provision dedicated cloud environment, initialize relational schema, and configure role-based operator logins.

  • Provisioned application host, SSL reverse proxy, and isolated PostgreSQL database instance.
  • Created core relational tables covering tickets, gate scans, staff KYC, attendance, expenses, and ledger journals.
  • Implemented scrypt password hashing, HTTP-only signed sessions, and 5-role RBAC permissions.
Day 02
21 Nov 2026Ticketing & Gate POSCompleted

Legacy 9-category tariff model and counter POS workflow

Build fast keyboard-driven counter POS screen matching all 9 visitor and camera tariffs with 80mm thermal slip layout.

  • Configured all 9 visitor and camera ticket categories with editable GST rates and SAC 999641 tagging.
  • Built single-screen counter POS supporting cash, UPI, EDC card, bank transfer, and concession remarks.
  • Added 80mm thermal slip formatting engineered for fast physical gate printing.
Day 03
22 Nov 2026Ticketing & Gate POSIn progress

Signed QR generation and single-entry gate scanner

Implement HMAC-signed QR ticket codes, gate scan verification, IST date validation, and duplicate entry protection.

  • Wiring HMAC-signed QR payload generation and cryptographic signature verification per receipt.
  • Adding IST visit-date mismatch detection with owner/manager override logging at entry gates.
  • Connecting webcam BarcodeDetector live QR scan fallback alongside manual gate code entry.
Day 04
23 Nov 2026Ticketing & Gate POSScheduled

Online visitor booking, Razorpay checkout, and reprint audit

Build visitor self-booking flow, Razorpay payment signature verification, and tracked ticket reprint/cancellation actions.

Scheduled for 23 Nov 2026
Day 05
24 Nov 2026Ticketing & Gate POSScheduled

End-of-day counter closing register and manager approval

Add shift-end physical cash denomination tally, digital totals check, variance capture, and owner/manager sign-off.

Scheduled for 24 Nov 2026
Day 06
25 Nov 2026HR & Staff OperationsScheduled

Staff repository, self-onboarding, and verified KYC vault

Create central staff profile directory with strict Aadhaar, PAN, and IFSC checks plus uploaded KYC document viewing.

Scheduled for 25 Nov 2026
Day 07
26 Nov 2026HR & Staff OperationsScheduled

Daily attendance, overtime tracking, and weekly roster builder

Build daily gate attendance sheet, overtime logging, leave status, and automated Monday to Sunday shift scheduling.

Scheduled for 26 Nov 2026
Day 08
27 Nov 2026HR & Staff OperationsScheduled

Monthly payroll computation and PNB payout register

Automate monthly basic/HRA/overtime calculation, salary slip generation, incentives export, and PNB payment journal posting.

Scheduled for 27 Nov 2026
Day 09
28 Nov 2026Expenses & ApprovalsScheduled

Expense intake, bill uploads, and approval controls

Create expense submission register with receipt attachments, category and vendor grouping, and logged rejection reasons.

Scheduled for 28 Nov 2026
Day 10
29 Nov 2026Accounting & GSTScheduled

Double-entry ledger, opening balances, and auto-posting

Implement chart of accounts covering cash, PNB, EDC/Razorpay clearing, GST ledgers, and automated double-entry journals.

Scheduled for 29 Nov 2026
Day 11
30 Nov 2026Accounting & GSTScheduled

Supplier invoice OCR and purchase bill verification

Build multi-tier PDF and image invoice text extraction to pre-fill supplier GSTIN, HSN/SAC, CGST, SGST, and IGST fields.

Scheduled for 30 Nov 2026
Day 12
1 Dec 2026Accounting & GSTScheduled

GSTR-2B matching, GSTR-3B export, and PNB settlement match

Build GST filing period matching via official GSTR-2B JSON/CSV uploads, GSTR-3B summary export, and EDC/Razorpay UTR reconciliation.

Scheduled for 1 Dec 2026
Day 13
2 Dec 2026Owner Dashboard & ExportsScheduled

Owner P&L dashboard, seasonality view, and scheduled reports

Build owner cockpit with footfall trends, Karnataka tourist season comparisons, monthly P&L table, and PDF/Excel/CSV exports.

Scheduled for 2 Dec 2026
Day 14
3 Dec 2026Cloud & Counter ReadinessScheduled

WhatsApp/email digests and encrypted nightly backups

Configure daily and weekly owner digest schedules, staff roster messaging, and automated encrypted database backups.

Scheduled for 3 Dec 2026
Day 15
4 Dec 2026Cloud & Counter ReadinessScheduled

End-to-end QA, CSV master templates, and operator handbook

Complete final verification across counter roles, package CSV import templates for tariffs and staff, and deliver operator handbook.

Scheduled for 4 Dec 2026

Post-delivery rollout plan (5 Dec to 15 Dec)

Phased transition from counter trial to full gate operation.

5 Dec 2026

Counter Hardware & Printer Trial

On-site test at Gate Counter 1 and Gate Counter 2 with live 80mm thermal slip printing, QR gate scanning, and Pine Labs EDC settlement checks.

6 to 14 Dec 2026

Parallel Run & Staff Onboarding

Cashiers, HR, and accounts teams verify opening ledger balances, upload staff KYC, and run real daily closings alongside legacy reports.

15 Dec 2026

Full Live Go-Live (Buffer until 1 Jan)

Official switch-over across physical counters, online QR booking, daily 7:00 PM owner digests, and accounting exports with buffer coverage through 1 Jan.

Livetree inputs needed before 5 Dec trial

7 operational and credential prerequisites ahead of gate testing.

  1. 01
    Counter PCs & 80mm thermal printer accessLivetree

    Station desktop/laptop browser test and thermal printer driver access ahead of the 5 December trial.

  2. 02
    Final tariff card & GST concession rulesLivetree

    Sign-off on the 9 category rates, complimentary pass rules, and GST rate confirmation before counter lock.

  3. 03
    Razorpay & Pine Labs EDC merchant credentialsLivetree

    Production Razorpay Key ID/Secret and Pine Labs terminal IDs mapped to the PNB collection account.

  4. 04
    WhatsApp template approval & SMTP mailboxShared

    MSG91 sender ID, approved QR ticket and roster templates, plus sender email credentials for owner digests.

  5. 05
    PNB account details & opening trial balanceLivetree

    Sample PNB statement format for UTR matching along with verified opening ledger balances as of cutover date.

  6. 06
    GSTIN details & sample GSTR-2B exportLivetree

    Palace operating GSTIN verification and sample monthly GSTR-2B portal JSON or CSV file for supplier matching.

  7. 07
    Active staff master & KYC batchLivetree

    Confirmed staff phone numbers, base salary structure, assigned counter, and existing Aadhaar/PAN copies.